New water connections: what the self-lay market actually offers developers

This post was originally published on this site.

The choice is real, but it is narrower and more procedural than most first-time developers expect, and the parts of the job that can be competed for are defined by the water company that will eventually own the pipe.

Understanding where that line falls is the difference between a useful second price and a wasted fortnight. Plenty of developers find out about self-lay halfway through the process, after a quotation has already landed, and assume the option has closed. Usually it hasn’t.

Who is allowed to lay a new water main

Work on a new water connection splits into contestable and non-contestable elements. Contestable work can be carried out by the water company, by an accredited self-lay organisation appointed by the developer, or in some cases by a new appointee, and it typically covers the new mains, the service pipes and much of the on-site construction. Non-contestable work stays with the appointed water company, and in most regions that includes the final connection into the live network and the point at which water is let into the new main.

Free newsletters

The stories that matter to UK business, straight to your inbox.

The precise boundary is not fixed in legislation. Each water company publishes an addendum to the sector code of practice for self-laying of water mains and services, setting out which activities it treats as contestable in its own area. A developer building across two supply areas can genuinely face two different answers to the same question, so the sensible first move is to pull the relevant company’s current developer services and self-lay documentation before pricing anything. Ofwat’s overview of the connections market is a reasonable starting point for anyone meeting the terminology for the first time.

Adoption is the other half of the arrangement. Whoever installs the pipework, the water company adopts the finished infrastructure into the public network once it complies with the adoption agreement and the associated testing and assurance requirements. Ofwat’s Code for Adoption Agreements sits behind that process, requiring companies to publish sector guidance and model adoption agreements that developers and self-lay organisations can work from.

What WIRS accreditation covers, and what it doesn’t

The Water Industry Registration Scheme is the accreditation water companies rely on when deciding whether a contractor’s work can be adopted, and it is currently administered by LRQA. Assessment covers the technical areas a self-lay organisation operates in, and the scheme exists so that an accredited firm is recognised across water companies rather than having to secure approval company by company. A developer can check any contractor’s current status on the WIRS register in about a minute.

Accreditation scope is where care is needed. WIRS registration is granted for specific activities, so a contractor accredited for service pipes is not automatically accredited for new mains, and a firm accredited for construction may not hold every category a particular scheme requires. Asking which categories a contractor holds, rather than asking whether they are accredited, is the question that separates a straightforward job from a stalled one. Accreditation also does not override the water company’s own technical standards, witnessing requirements or defect liability terms, all of which still apply.

Taking approved drawings to an accredited contractor

The most common misunderstanding in the whole process concerns approved drawings. A developer who has applied to the water company, paid for the scheme to be worked up and received approved drawings alongside a quotation has not committed to that company carrying out the construction. Approval attaches to the scheme, not to the contractor, and the contestable elements remain open.

That matters commercially because the approved drawings are a complete package: pipe sizes, routes, materials, fittings and connection points are all fixed and signed off. A developer holding those drawings can send them out for pricing exactly as any other subcontract package would go out, and compare like with like rather than comparing two different interpretations of the same site. Contractors working in this market, among them the Hertfordshire-based utility contractor McFadden Utilities, will provide an alternative quote for a new water connection against drawings the water company has already approved, with the water company retaining approval, inspection and adoption of the finished works throughout. The initial approach to the water company still comes from the developer, and the accredited contractor picks the process up from the point where the scheme is agreed.

None of this is adversarial. Water companies set the standards the assets have to meet and then carry those assets for the next century, which is why the assurance requirements are as detailed as they are. Many accredited self-lay organisations also work under contract to water companies on repair, maintenance and mains work, so the same crews turn up on both sides of the arrangement. Competition in this market was designed into it by the regulator rather than fought for against the companies.

Where the money and the time actually move

Cost differences in self-lay come from three places, and claims of dramatic savings usually rest on only one of them applying. The first is the construction price itself, which is a straightforward competitive tender once the drawings are fixed. The second is the asset payment, the sum a water company pays for the value of the infrastructure it adopts, which offsets against the developer’s costs and is calculated under the company’s published charging arrangements. The third is coordination, and on multi-utility sites it is often the largest of the three, because a single groundworks operation covering water alongside other services means one set of excavations, one reinstatement and one traffic management exercise rather than three.

Programme is the other reason developers look at self-lay, and the honest position is that self-lay moves the construction window into the developer’s control while leaving the application, approval and adoption stages where they always were. A contractor cannot compress the water company’s approval process, and any firm suggesting otherwise is worth a second look.

The questions worth asking before appointing

Four checks cover most of the risk. Confirm the contractor’s WIRS categories match the actual works. Confirm which elements the local water company treats as non-contestable, and who is pricing them. Confirm who is responsible for testing, chlorination, as-built records and defect remedy during the liability period. And confirm the reinstatement specification, because unsatisfactory reinstatement on an adopted highway becomes the developer’s problem long after the water is flowing.

Self-lay is not the right answer to every scheme. For a single connection off an existing main in a straightforward location, the water company’s own quotation is frequently the simplest route and the difference is marginal. For anything involving new mains, phased plots, awkward crossings or a tight build programme, a second price from an accredited contractor is cheap information, and the drawings a developer already holds are all that’s needed to get one.